Review of performance
Outputs and contribution to outcomes 2004–05
The Commission is included in the Department of Prime Minister and Cabinet’s Portfolio Budget Statements. The Public Service Commissioner, as the head of the Commission, is responsible for the Commission’s financial and human resources and for assessing the level of the Commission’s achievement against its output structure.
Performance information, as described in the 2004–05 Portfolio Budget Statement which relates to the Merit Protection Commissioner’s functions, can be aggregated, where relevant, from Tables M1 and M2 of this report. Table M1 comprises casework arising from APS agencies and Table M2 includes casework arising from both APS and non-APS agencies.
Table M1: Review of actions—workload, work completed and timeliness, 1 July 2004 to 30 June 2005
| Cases | Promotion Review Committees | Primary review–Code of Conduct | Primary review–other | Secondary review | Review –former employees |
| On hand at start of year | 9 | 6 | 0 | 14 | 0 |
| Received during the year | 185 | 41 | 21 | 87 | 11 |
| Reviewed | 99 | 26 | 7 | 45 | 6 |
| Not accepted | 12 | 2 | 6 | 43 | 1 |
| Lapsed or withdrawn | 49 | 7 | 4 | 2 | 1 |
| Total finalised during the year | 160 | 35 | 17 | 90 | 8 |
| On hand at end of year | 34 | 12 | 4 | 11 | 3 |
| Target completion time (weeks) | 6 | 10 | 10 | 8 | 10 |
| Average completion time for reviewed cases (weeks) | 6.91 | 18.87 | 9.98 | 14.42 | 6.3 |
| Completed within target time (number) | 51 | 6 | 2 | 13 | 6 |
| Completed within target time (%) | 52 | 24 | 29 | 29 | 100 |
Table M2: Fee-for-service functions—workload and work completed, 1 July 2004 to 30 June 2005
| Independent Selection Advisory Committees | Other services requested | |
| On hand at start of year | 15 | 28 |
| Received during the year | 94 | 343 |
| Completed | 58 | 289 |
| Lapsed/withdrawn | 8 | 40 |
| Total finalised during the year | 66 | 329 |
| On hand at end of year | 43 | 42 |